| dc.description.abstract | This study presents the technical design, stochastic simulation, and economic optimisation of an on-site greywater recycling system for a representative manufacturing facility in Ulaanbaatar, Mongolia. Driven by accelerating water scarcity and the strategic objectives of the Millennium Challenge Corporation (MCC) Mongolia Water Compact, the research develops a five-unit treatment train (screening → equalization/sedimentation → sand filtration → UV disinfection → treated storage), constructs a physically rigorous two-tank daily water-balance simulation with Monte Carlo analysis (100 stochastic scenarios per configuration), conducts a Life-Cycle Cost Analysis (LCCA) over 20 years including equipment replacement costs and salvage value, and employs a three-dimensional combinatorial optimisation across 4,560 configurations to identify the most cost-effective and reliable design. The simulation explicitly models the Equalization/Sedimentation Tank (TK-101) and the Treated Water Storage Tank (TK-102) as independent daily state variables with treatment efficiency (η = 0.95), maintenance downtime, and realistic weekend and holiday demand patterns, accurately capturing the hydraulic buffering dynamics that single-tank simplifications fail to represent. The optimal configuration — V_eq = 6 m³ equalization tank, Q_treat = 40 m³/day treatment capacity, S_max = 12 m³ treated storage — achieves a mean reliability of 97.2% (P5 = 95.3% across Monte Carlo runs), a CAPEX of 94.8 million MNT, and a 20-year NPV of approximately −71.3 million MNT, with a payback period of approximately 3 years. These findings confirm that industrial greywater reuse is technically robust and economically compelling under Mongolian conditions, and the framework is designed to accept real facility data with minimal structural modification. | |
| dc.identifier.other | B2200569 | |
| dc.identifier.uri | https://gmitlibrary.net/handle/123456789/277 | |
| dc.language.iso | en | |
| dc.publisher | GMIT | |
| dc.subject | greywater recycling | |
| dc.subject | two-tank water balance | |
| dc.subject | Monte Carlo simulation | |
| dc.subject | life-cycle cost analysis | |
| dc.subject | industrial water reuse | |
| dc.subject | Ulaanbaatar | |
| dc.subject | Mongolia | |
| dc.subject | equalization tank | |
| dc.subject | stochastic modelling | |
| dc.subject | combinatorial optimisation | |
| dc.title | Design and Optimisation of an On-Site Greywater Recycling System for a Manufacturing Facility in Ulaanbaatar, Mongolia | |